Short answer: Dubai’s Roads and Transport Authority (RTA) opens the last bridge of the World Trade Centre Roundabout Development Project on Friday 30 October 2026. It is a 1,000-metre, two-lane bridge built for about 3,000 vehicles an hour. With it, all major works on the project are complete: five bridges with a combined length of 5km, at a cost of more than Dh696 million.
The project links Sheikh Zayed Road with Sheikh Khalifa bin Zayed Street, Sheikh Rashid Street, 2nd December Street, Za’abeel Palace Street and Al Majlis Street, and the old roundabout has been converted into an at-grade intersection. RTA says the trip between Al Majlis Street and 2nd December Street drops from six minutes to one minute, and the average delay at the intersection falls from 12 minutes to 90 seconds.
The five bridges at a glance
| Link | Bridges | Combined length | Capacity (vehicles an hour) | Status |
|---|---|---|---|---|
| Sheikh Zayed Road towards Sheikh Khalifa bin Zayed Street and Deira | 1 | 1,000 m (two lanes) | About 3,000 | Opens Friday 30 October 2026 (final bridge) |
| Sheikh Rashid Street to 2nd December Street | 2 | 2,000 m | Up to 6,000 | Earlier phase |
| Al Majlis Street to 2nd December Street | 2 | 2,000 m | About 6,000 | Earlier phase |
| Total | 5 | 5,000 m | Project cost: more than Dh696 million |
Reports describe the direction of the final bridge slightly differently: Khaleej Times and Gulf News give it as Sheikh Zayed Road to Sheikh Khalifa bin Zayed Street towards Deira, while Gulf Business describes it as carrying traffic from Al Majlis Street towards 2nd December Street. Follow the road signs on the day.
Who will notice the difference
RTA estimates the project serves more than 500,000 residents and visitors. The areas it serves include Dubai World Trade Centre, DIFC, Za’abeel, Al Satwa, Al Karama, Al Jafiliya and Al Mankhool. If you drive between these areas and Sheikh Zayed Road, or to events at the World Trade Centre, this is the junction that changes.
What has not been announced
- The opening time on Friday. None of the reports gives an hour, so expect the new lanes to appear some time on 30 October.
- Any closures or diversions on the day. None have been reported. Check the RTA app or its social media channels before you set off.
- Salik. Nothing in the announcement mentions tolls. Our Salik timings and charges guide lists the current gates and prices.
RTA’s separate Al Mustaqbal Street project, which adds about 1.5km of bridges and tunnels and raises capacity by around 33%, is scheduled for completion in 2027. Al Mustaqbal Street is also one of the five Dubai roads where speed limits change from 1 November 2026, so drivers in this part of the city have two changes to note within days of each other.
Quick answers
When does the final World Trade Centre Roundabout bridge open?
On Friday 30 October 2026. RTA has not said at what time of day it will open to traffic.
How much time will the new bridges save?
RTA says the trip between Al Majlis Street and 2nd December Street falls from six minutes to one minute, and the average delay at the intersection falls from 12 minutes to 90 seconds.
How much did the World Trade Centre Roundabout project cost?
More than Dh696 million, for five bridges with a combined length of 5km.
More on driving in Dubai: UAE traffic fines and black points · daily commute options and costs.
Published 27 October 2026. Sources: Roads and Transport Authority announcement as reported by Khaleej Times (25 October 2026), Gulf News (25 October 2026) and Gulf Business (25 October 2026, citing WAM). We will update this post if RTA announces an opening time or diversions.